In 2015, the floods caused by Storm Desmond wreaked devastating havoc throughout the Lake District, with flood levels inside buildings measuring over 1m deep.

BuildzoneUK were commissioned to carry out reinstatement works to the Trespass store, having previously helped Trespass with flood damage back in 2009.

This work pertained to strip out and reinstatement of one floor in the property, 2015’s flood required both floors to be worked on. Initial works comprised of the stripping out of the store, drying out and specialised cleaning to ensure no damp remained.

Interior works comprised of, joinery, decoration, floor finishes and full M&E installation. Stud walls and frames were completed, creating areas in the store for visual merchandising displays. At the client’s request, BuildzoneUK also moved the staircase to the first floor and added a new stud wall below this, changing the layout of the store.

External works consisted of decoration, installing new signage and replacing rotten timbers.

Happily, the BuildzoneUK team made a lasting good impression on the client, and were commissioned to carry out further cosmetic refurbishments at the store.

Download the case study

Project details:

Type: Flood damage
Timeframe: 22 weeks
Value: £40,000

Key sectors

Education
Healthcare
Cladding
Insurance
Passive Fire Protection
Listed buildings

RETAIL PREMISES

Ryehope retail outlet

In 2015, the floods caused by Storm Desmond wreaked devastating havoc throughout the Lake District, with flood levels inside buildings measuring over 1m deep.

BuildzoneUK were commissioned to carry out reinstatement works to the Trespass store, having previously helped Trespass with flood damage back in 2009.

This work pertained to strip out and reinstatement of one floor in the property, 2015’s flood required both floors to be worked on. Initial works comprised of the stripping out of the store, drying out and specialised cleaning to ensure no damp remained.

Interior works comprised of, joinery, decoration, floor finishes and full M&E installation. Stud walls and frames were completed, creating areas in the store for visual merchandising displays. At the client’s request, BuildzoneUK also moved the staircase to the first floor and added a new stud wall below this, changing the layout of the store.

External works consisted of decoration, installing new signage and replacing rotten timbers.

Happily, the BuildzoneUK team made a lasting good impression on the client, and were commissioned to carry out further cosmetic refurbishments at the store.

Download the case study

Project details:

Type: Flood damage
Timeframe: 22 weeks
Value: £40,000

Key sectors

Education
Healthcare
Cladding
Insurance
Passive Fire Protection
Listed buildings

RETAIL PREMISES

Ryehope retail outlet

In 2015, the floods caused by Storm Desmond wreaked devastating havoc throughout the Lake District, with flood levels inside buildings measuring over 1m deep.

BuildzoneUK were commissioned to carry out reinstatement works to the Trespass store, having previously helped Trespass with flood damage back in 2009.

This work pertained to strip out and reinstatement of one floor in the property, 2015’s flood required both floors to be worked on. Initial works comprised of the stripping out of the store, drying out and specialised cleaning to ensure no damp remained.

Interior works comprised of, joinery, decoration, floor finishes and full M&E installation. Stud walls and frames were completed, creating areas in the store for visual merchandising displays. At the client’s request, BuildzoneUK also moved the staircase to the first floor and added a new stud wall below this, changing the layout of the store.

External works consisted of decoration, installing new signage and replacing rotten timbers.

Happily, the BuildzoneUK team made a lasting good impression on the client, and were commissioned to carry out further cosmetic refurbishments at the store.

Download the case study

Key sectors

Education
Healthcare
Cladding
Insurance
Passive Fire Protection
Listed buildings

Project details:

Type: Flood damage
Timeframe: 22 weeks
Value: £40,000

See also:

View project

See also:

View project

See also:

View project